[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},903288,584,1,"单选题","水泥混凝土路面施工每天摊铺结束或因临时原因中断时，应设置横向施工缝，下列关于横缝说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","横向胀缝应采用假缝",false,{"key":16,"text":17,"correct":14},"B","横向缩缝宜不等间距布置",{"key":19,"text":20,"correct":14},"C","横向施工缝在缩缝处应采用拉杆企口缝",{"key":22,"text":23,"correct":24},"D","横缝从功能上可分为横向施工缝、横向缩缝、横向胀缝",true,"A项，横向胀缝作用是使水泥混凝土板在温度升高时能自由伸展，应采用真缝。B项，普通混凝土路面横向缩缝宜等间距布置，不宜采用斜缩缝和不等间距缩缝。C项，横缝其位置宜与胀缝或缩缝重合，横向施工缝在缩缝处应采用设传力杆平缝型，确有困难不能重合时，横向施工缝应采用拉杆企口缝。D项，横缝从功能上可分为：横向施工缝、横向缩缝、横向胀缝，横缝从构造上分为设传力杆平缝型和设拉杆企口缝型；横缝还可分为设传力杆假缝型和不设传力杆假缝型。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]