[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903287,584,1,"单选题","下列无机结合料稳定类基层和底基层施工说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水泥稳定土基层应采用路拌法施工",false,{"key":16,"text":17,"correct":18},"B","石灰稳定土基层施工气温应不低于5℃",true,{"key":20,"text":21,"correct":14},"C","石灰稳定土基层每层最小压实厚度为200mm",{"key":23,"text":24,"correct":14},"D","石灰粉煤灰稳定土基层养护期不得少于3天","A项，水泥稳定土基层应采用厂拌法施工，石灰稳定土和石灰粉煤灰稳定土可采用路拌法或厂拌法施工。BC两项，石灰稳定土基层施工气温应不低于5℃。并在第一次重冰冻到来之前一个月完成。压实厚度每层不小于100mm，也不超过200mm。D项，石灰粉煤灰稳定土基层碾压完成后应及时养护，养护期不少于7天，应始终保持表面潮湿。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]