[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903286":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},903286,584,1,"单选题","下列垫层施工中符合规定的做法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","垫层材料选用砂砾或水泥稳定土",true,{"key":16,"text":17,"correct":18},"B","在铺筑垫层前，应清除路基面，保证路基干燥",false,{"key":20,"text":21,"correct":18},"C","摊铺后的碎石、砂砾应采用粗集料做嵌缝处理",{"key":23,"text":24,"correct":18},"D","两段作业衔接处，第一段留下3～6m不进行碾压","垫层材料可选用碎石、砂砾、煤渣、矿渣等粒料以及水泥稳定土、石灰稳定土等。垫层的施工要求如下：①应在验收合格的路基上铺筑垫层材料，在铺筑垫层前，应清除路基面，并洒水湿润；②应采用批准的机械进行摊铺，摊铺后的碎石、砂砾应无明显离析现象，或采用细集料做嵌缝处理；③经过整平和整型，应按试验路段所确认的压实工艺，在全宽范围内均匀地压实至重型击实最大密度的96%以上，一个路段碾压完成以后。应按批准的方法做密实度试验；④凡压路机不能作业的地方，应采用机夯进行压实；⑤严禁压路机在已完成的或正在碾压的路段上掉头和紧急制动；⑥两段作业衔接处，第一段留下5～8m不进行碾压，第二段施工时，将前段留下未压部分与第二段一起碾压。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]