[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903243":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},903243,584,1,"单选题","下列关于土质路堤的压实要求符合规定的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","压实过程中，直线段由两边向中间进行",true,{"key":16,"text":17,"correct":18},"B","压实机具应先重后轻",false,{"key":20,"text":21,"correct":18},"C","碾压速度宜先快后慢",{"key":23,"text":24,"correct":18},"D","碾压一段终了，不宜采取机械纵向退行方式碾压第二遍","土质路堤的压实要求包括：①压实机械碾压时，一般以慢速效果最好，除羊足碾或凸块式碾外，压实速度以2～4km\u002Fh为宜。②压实机具应先轻后重，以便能适应逐渐增长的土基强度。③碾压速度宜先慢后快。④碾压一段终了时，宜采取机械纵向退行方式碾压第二遍，不宜掉头以免搓挤土。⑤在整个全宽的填土上压实，宜纵向分行进行，直线段由两边向中间，曲线段由曲线的内侧向外侧。两行之间的接头一般应重叠1\u002F4～1\u002F3轮迹，三轮压路机应重叠后轮的1\u002F2。⑥纵向分段碾压好后进行第二段压实时，纵向接头处的碾压范围宜重叠1～2m，以确保接头处平顺过渡。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]