[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903231":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903231,584,1,"单选题","填方分几个作业段施工时，接头部位如不能交替填筑，则先填路段，应按1：1坡度分层留台阶；如能交替填筑，则应分层相互交替搭接，搭接长度不小于（ ）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","本题考查的是路基施工技术。路堤填筑时，应从最低处起分层填筑，逐层压实； 当原地面纵坡大于12%或横坡陡于1：5时，应按设计要求挖台阶，或设置坡度向内并大于4%、宽度大于2m的台阶。填方分几个作业段施工时，接头部位如不能交替填筑，则先填路段，应按1：1坡度分层留台阶；如能交替填筑，则应分层相互交替搭接，搭接长度不小于2m。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]