[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903230":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},903230,584,1,"单选题","水泥稳定土基层用18～20t压路机碾压时，每层的压实厚度不应超过（ ）mm。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","100",false,{"key":16,"text":17,"correct":14},"B","150",{"key":19,"text":20,"correct":21},"C","200",true,{"key":23,"text":24,"correct":14},"D","250","本题考查的是路面工程。混合料压实，用12～15t压路机碾压时，每层的压实厚度不应超过150mm；用18～20t压路机碾压时，每层的压实厚度不应超过200mm；每层最小压实厚度为100mm。当压实厚度超过上述规定时，应分层摊铺。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]