[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903223":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903223,584,1,"单选题","砾（碎）石桩施工采用振动沉管法，施工顺序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先里排后外排，隔排隔桩跳打",false,{"key":16,"text":17,"correct":18},"B","先外排后里排，隔排隔桩跳打",true,{"key":20,"text":21,"correct":14},"C","先外排后里排，依次顺序施打",{"key":23,"text":24,"correct":14},"D","先里排后外排，依次顺序施打","本题考查的是路基施工技术。粒料桩直径为0.6～0. 8m，以冲击或振动方法强力将粒料挤入软弱土地基。砾（碎）石桩施工采用振动沉管法，施工顺序为先外排后里排，隔排隔桩跳打；桩体应连续密实，不得有断桩、缩径、夹砂等缺陷。主要用振冲器、起重机或施工专用平车和水泵，将砂、碎石、砂砾、废渣等粒料加入振密。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]