[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903222":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903222,584,1,"单选题","沥青混凝土路面施工应做（ ）的试验路段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","100m",false,{"key":16,"text":17,"correct":18},"B","200m",true,{"key":20,"text":21,"correct":14},"C","300m",{"key":23,"text":24,"correct":14},"D","400m","本题考查的是路面工程。进行热拌沥青碎石的配合比设计，即包括目标配合比设计阶段、生产配合比设计阶段、生产配合比验证阶段。配合比设计采用马歇尔试验设计方法；施工前，承包人应做200m的试验路段；试验路段验收合格后方可施工。试验段应分为试拌和试铺两个阶段。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]