[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903217":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903217,584,1,"单选题","混凝土板养护初期，严禁人、畜、车辆通行，在达到设计强度（ ）后，行人方可通行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30%",false,{"key":16,"text":17,"correct":18},"B","40%",true,{"key":20,"text":21,"correct":14},"C","75%",{"key":23,"text":24,"correct":14},"D","80%","本题考查的是路面工程。混凝土板养护初期，严禁人、畜、车辆通行，在达到设计强度40%后，行人方可通行。在路面养护期间，平交道口应搭建临时便桥。面板达到设计弯拉强度后，方可开放交通。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]