[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},903202,584,1,"单选题","标后设计编制过程中包括：①设计施工平面图；②编制施工准备工作计划；③确定施工部署；④拟定施工方案；⑤计算技术经济指标。正确的排序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","③—①—⑤—④—②",false,{"key":16,"text":17,"correct":14},"B","④—①—⑤—②—③",{"key":19,"text":20,"correct":14},"C","④—②—⑤—①—③",{"key":22,"text":23,"correct":24},"D","③—④—②—①—⑤",true,"标后设计的编制步骤为：进行调查研究，获得编制依据→确定施工部署→拟定施工方案→编制施工进度计划→编制各种资源需要量计划及运输计划→编制供水、供热、供电计划→编制施工准备工作计划→设计施工平面图→计算技术经济指标。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]