[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903193":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},903193,584,1,"单选题","采用三阶段设计的工程，在技术设计阶段应提出（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工方案",false,{"key":16,"text":17,"correct":18},"B","修正的施工方案",true,{"key":20,"text":21,"correct":14},"C","施工组织计划",{"key":23,"text":24,"correct":14},"D","施工组织设计","本题考查的是公路工程施工组织设计。采用三阶段设计的工程，在技术设计阶段应提出修正的施工方案。修正施工方案应根据初步设计的审批意见和需要进一步解决的问题进行编制。修正施工方案解决问题的深度和提交文件的内容，介于施工方案和施工组织计划之间。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]