[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-903114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},903114,584,1,"单选题","公路项目的环境保护主要项目不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可行性研究阶段项目环境影响评价",true,{"key":16,"text":17,"correct":18},"B","初步设计阶段项目环境影响评价",false,{"key":20,"text":21,"correct":18},"C","施工图设计阶段的环境保护设计",{"key":23,"text":24,"correct":18},"D","施工期的环境保护设施的施工及监理","公路项目的环境保护主要项目包括：①初步设计阶段项目环境影响评价；②施工图设计阶段的环境保护设计；③招投标阶段在招标文件、工程合同及监理合同中纳入环境保护条款；④施工期的环境保护设施的施工及监理：⑤竣工和交付使用阶段的环境保护设施验收与环境后评价；⑥公路运营期的环境保护设施的运行及维护。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]