[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902898":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},902898,584,1,"单选题","下列关于T形梁和工形梁施工图预算要求的说法中，不正确的是.（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制简支T形梁和工形梁的施工图预算时，不应列入修建预制场地",true,{"key":16,"text":17,"correct":18},"B","编制简支T形梁和工形梁的施工图预算时，应列入修建大型预制构件的平面底座",false,{"key":20,"text":21,"correct":18},"C","预制场内还应计列起吊的龙门架和运输轨道，以利构件起吊出坑和运输工作",{"key":23,"text":24,"correct":18},"D","修建大型预制构件平面底座的数量以预制梁肋的根数与施工期限为依据计算确定","本题考查的是桥梁上部构造。编制简支T形梁和工形梁的施工图预算时，除应列入修建预制场地外，还要列入修建大型预制构件的平面底座，其数量应以预制梁肋的根数与施工期限为依据计算确定。要求尽可能多次周转使用，以节约工程费用。同时，预制场内还应计列起吊的龙门架和运输轨道，以利构件起吊出坑和运输工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]