[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902844":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},902844,584,1,"单选题","明洞拱圈外模拆除、拱圈混凝土达到设计强度的（ ）后，应及时按设计规范要求施作防水层及拱脚纵向排水沟、环向盲沟。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50%",true,{"key":16,"text":17,"correct":18},"B","60%",false,{"key":20,"text":21,"correct":18},"C","79%",{"key":23,"text":24,"correct":18},"D","80%","本题考查的是隧道主体建筑物。明洞拱圈外模拆除、拱圈混凝土达到设计强度的50%后，应及时按设计规范要求施作防水层及拱脚纵向排水沟、环向盲沟，防水板应向隧道内延伸不小于0.5m，并与暗洞防水板连接良好。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（交通）","建筑工程",0]