[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902637":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":23,"analysis":24},902637,583,2,"多选题","（2016年考题）依据《通用安装工程工程量计算规范》（GB50856--2013），静置设备安装中的整体容器安装项目，根据项目特征描述范围，其他工作内容除包括容器安装，吊耳制作，安装外，还包括（）。 A.设备填充 B.压力试验 C.清洗、脱脂、钝化 D.灌浆",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":16},"C",{"key":20,"text":20,"correct":16},"D",{"key":22,"text":22,"correct":13},"E","BCD","本题考查的是静置设备工程计量。静置设备安装一整体容器安装其工作内容包括：（1）塔器安装；（2）吊耳制作、安装；（3）压力试验；（4）清洗、脱脂、纯化；（5）灌浆。",{"id":6,"name":26,"category":27,"favorite":28},"建设工程技术与计量（安装)","建筑工程",0]