[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902596":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":23,"analysis":24},902596,583,2,"多选题","（2020年真题）当拟建工程中有易燃易爆、有害环境下的工程,可列项（ ）。 A.压力试验 B.设备、管道施冮的安全防冻和焊接保护 C.管道安拆后的充气保护 D.吹扫",[11,14,17,19,21],{"key":12,"text":12,"correct":13},"A",false,{"key":15,"text":15,"correct":16},"B",true,{"key":18,"text":18,"correct":16},"C",{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":13},"E","BC","P121-122 当拟建工程中有设备、管道冬雨季施工,有易燃易爆、有害环境施工,或设备、管道焊接质量要求较高时,措施项目清单可列项“设备、管道施工的安全防冻和焊接保护”。",{"id":6,"name":26,"category":27,"favorite":28},"建设工程技术与计量（安装)","建筑工程",0]