[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902593":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":23,"analysis":24},902593,583,2,"多选题","（2016年考题）依据《通用安装工程工程量计算规范》（GB50856--2013），脚手架搭拆措施项目包括的工作内容有（）。 A.场内、场外相关材料搬运 B.搭设、拆除脚手架 C.搭设、超出围护网 D.拆除脚手架后材料的堆放",[11,14,16,19,21],{"key":12,"text":12,"correct":13},"A",true,{"key":15,"text":15,"correct":13},"B",{"key":17,"text":17,"correct":18},"C",false,{"key":20,"text":20,"correct":13},"D",{"key":22,"text":22,"correct":18},"E","ABD","本题考查的是措施项目清单。脚手架搭拆：场内、场外材料搬运，搭、拆脚手架，拆除脚手架后材料的堆放。",{"id":6,"name":26,"category":27,"favorite":28},"建设工程技术与计量（安装)","建筑工程",0]