[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902583":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},902583,583,2,"多选题","（2019年考题）依据《通用安装工程工程量计算规范》（G",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","50856-2013）,在编制某建设项目分部分项工程量清单时，必须包括五部分内容,其中有（）。",true,{"key":16,"text":17,"correct":14},"B","项目名称",{"key":19,"text":20,"correct":21},"C","项目编码",false,{"key":23,"text":24,"correct":21},"D","计算规则",{"key":26,"text":27,"correct":21},"E","工作内容","AB","在编制安装工程分部分项工程量清单时，应根据《安装工程计量规范》规定的项目编码、项目名称、项目特征、计量单位和工程量计算规则进行编制，即一个分部分项工程量清单必须包括五个要件:项目编码、项目名称、项目特征、计量单位和工程量这五个要件，缺一不可。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（安装)","建筑工程",0]