[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902523":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902523,583,2,"多选题","电缆接续环节包括的内容有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","模块的芯线复接",true,{"key":16,"text":17,"correct":18},"B","编排线序",false,{"key":20,"text":21,"correct":14},"C","扣式接线子的直接",{"key":23,"text":24,"correct":18},"D","接头封合","AC","教材p418。电缆接续顺序：拗正电缆→剖缆→编排线序→芯线接续前的测试→接续（包括模块直接、模块的芯线复接、扣式接线子的直接、扣式接线子的复接、扣式接线子的不中断复接） →接头封合。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]