[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902480":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902480,583,2,"多选题","电气线路工程中，电缆安装前进行检查实验，合格后方可进行敷设，对以上的电缆应做的实验为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直流耐压实验",true,{"key":16,"text":17,"correct":18},"B","交流耐压实验",false,{"key":20,"text":21,"correct":18},"C","局部放电实验",{"key":23,"text":24,"correct":14},"D","500V摇表检测","AD","2020版教材P363 电缆安装前检查及实验，电缆安装前要进行检查。1kV以上的电缆要做直流耐压试验，1kV以下的电缆用500V摇表测绝缘，检查合格后方可敷设。当对纸质油浸电缆的密封有怀疑时，应进行潮湿判断。直埋电缆、水底电缆应经直流耐压试验合格，充油电缆的油样应试验合格。电缆敷设时，不应破坏电缆沟和隧道的防水层。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]