[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902417":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902417,583,2,"多选题","球罐水压试验过程中要进行基础沉降观测，并做好实测记录。正确的观测时点为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","充水前",true,{"key":16,"text":17,"correct":18},"B","充水到1／2球罐本体高度",false,{"key":20,"text":21,"correct":14},"C","充满水24h",{"key":23,"text":24,"correct":14},"D","放水后","ACD","2020版教材P338 本题考查的是球罐的安装施工。球罐水压试验过程中要进行基础沉降观测，观测应分别在充水前、充水到1\u002F3 、充水到2\u002F3球罐本体高度、充满水24h和放水后各个阶段进行观测，并做好实测记录。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]