[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902389":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902389,583,2,"多选题","下列工业管道工程量计算规则叙述正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管件压力试验、吹扫、清洗、脱脂均包括在管道安装中",true,{"key":16,"text":17,"correct":18},"B","在主管上挖眼接管的三通和摔制异径管，均以支管径按管件安装工程量计算，不另计制作费和主材费",false,{"key":20,"text":21,"correct":14},"C","挖眼接管的三通支线管径小于主管径1／2时，不计算管件安装工程量",{"key":23,"text":24,"correct":18},"D","三通、四通、异径管均按小管径计算","AC","选项A正确，管件压力试验、吹扫、清洗、脱脂均包括在管道安装中。 选项B错误，选项C正确，在主管上挖眼接管的三通和摔制异径管，均以主管径按管件安装工程量计算，不另计制作费和主材费；挖眼接管的三通支线管径小于主管径1／2时，不计算管件安装工程量；在主管上挖眼接管的焊接接头、凸台等配件，按配件管径计算管件工程量。 选项D错误，三通、四通、异径管均按大管径计算。2020版教材P312-317",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]