[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902310":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902310,583,2,"多选题","水灭火系统的末端试水装置的安装包含（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","压力表",true,{"key":16,"text":17,"correct":14},"B","控制阀",{"key":19,"text":20,"correct":21},"C","连接管",false,{"key":23,"text":24,"correct":21},"D","排水管","AB","教材p185。末端试水装置以“组”计算，包括压力表、控制阀等附件安装。末端试水装置安装中不含连接管及排水管安装，其工程量并入消防管道。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]