[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902279":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902279,583,2,"多选题","根据《通用安装工程工程量计算规范》热力设备安装工程按设计图示设备质量以“t”计算的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","烟道、热风道",true,{"key":16,"text":17,"correct":14},"B","渣仓",{"key":19,"text":20,"correct":14},"C","脱硫吸收塔",{"key":22,"text":23,"correct":24},"D","除尘器",false,"ABC","2020版教材P168 烟道、热风道，冷风道，制粉管道，送粉管道，原煤管道应根据项目特征（管道形状，管道断面尺寸，管壁厚道）以“t”为计量单位 教材P169页，渣仓应根据项目特征以“t”为计量单位计算， 教材P170页，石粉仓，吸收塔应根据项目特征以t为计量单位。 除尘器要有据项目特征，以“台”为计量单位。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]