[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902248":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902248,583,2,"多选题","单价措施项目清单编制的主要依据是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工方法",true,{"key":16,"text":17,"correct":18},"B","施工平面图",false,{"key":20,"text":21,"correct":14},"C","施工方案",{"key":23,"text":24,"correct":18},"D","施工现场管理","AC","教材p121-122。单价措施项目清单编制的主要依据是施工方案和施工方法。总价措施项目编制的主要依据是施工平面图和现场管理。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]