[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902247":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902247,583,2,"多选题","以下列属项于是单（价措施）项。目清单编制的",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","非夜间施工增加",false,{"key":16,"text":17,"correct":18},"B","工程系统检测、检验",true,{"key":20,"text":21,"correct":14},"C","已完工程及设备保护",{"key":23,"text":24,"correct":18},"D","金属抱杆安装拆除、移位","BD","教材p118，121。单价措施项目清单编制：“平台铺设、拆除”， “设备、管道施工的防冻和焊接保护”， “工程系统检测、检验”， “焦炉烘炉、热态工程”， “管道安拆后的充气保护”， “隧道内施工的通风、供水、供气、供电、照明及通信设施”， “金属抱杆安装拆除、移位”。总价措施项目编制的列项。如“文明施工”、“夜间设施增加”、“非夜间施工增加”、“二次搬运”、“冬雨季施工增加”、“已完工程及设备保护”、“高层施工增加”等。对于所列项的措施项目，按“项”予以计量。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]