[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902240":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902240,583,2,"多选题","以下属于总价措施项目费是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","文明施工费",true,{"key":16,"text":17,"correct":18},"B","超髙施工增加",false,{"key":20,"text":21,"correct":14},"C","二次搬运",{"key":23,"text":24,"correct":18},"D","吊车加固","AC","教材p118。措施项目分为两类，无法对其工程量进行计量，称为总价措施项目，以“项”为计量单位进行编制，如：文明施工费，夜间施工，非夜间施工照明，二次搬运，冬雨季施工，地上、地下设施，建筑物的临时保护设施、已完工程及设备保护等；另一类是可以计算工程量的项目，称为单价措施项目，如：脚手架工程，垂直运输、超髙施工增加，吊车加固等。单价措施项目应按照分部分项工程项目清单的方式进行计量和计价。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]