[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902228":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902228,583,2,"多选题","依据《通用安装工程工程量计算规范》GB50856--2013的规定，属于安全文明施工及其他措施项目的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在有害身体健康环境中施工增加",false,{"key":16,"text":17,"correct":18},"B","环境保护",true,{"key":20,"text":21,"correct":18},"C","非夜间施工增加",{"key":23,"text":24,"correct":18},"D","高层施工增加","BCD","2020版教材P120 本题考查的是措施项目清单的内容。安全文明施工及其他措施项目中包括：环境保护、文明施工、安全施工、临时设施、夜间施工增加、非夜间施工增加、二次搬运、冬雨季施工增加、已完工程及设备保护、高层施工增加、其他。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]