[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902227":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902227,583,2,"多选题","在施工措施项目及其计量中，施工方案内容一般包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工方法和施工机械选择",true,{"key":16,"text":17,"correct":18},"B","工程系统检测",false,{"key":20,"text":21,"correct":14},"C","施工阶段划分",{"key":23,"text":24,"correct":14},"D","施工流向和施工顺序","ACD","2020版教材P121 本题的考点是施工措施项目及其计量。 单价措施项目清单编制的主要依据是施工方案和施工方法。施工方案内容一般包括施工流向、施工顺序、施工阶段划分、施工方法和施工机械选择等内容，还包括招标文件、施工规范与工程验收规范和设计文件对工程所要求的技术措施而采用的一些施工方法。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]