[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902224":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902224,583,2,"多选题","依据《通用安装工程工程量计算规范》GB50856-2013的规定，附录H工业管道工程中低压碳钢管安装的“工程内容”，有安装、压力试验、吹扫，还包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","清洗",true,{"key":16,"text":17,"correct":14},"B","脱脂",{"key":19,"text":20,"correct":21},"C","钝化",false,{"key":23,"text":24,"correct":21},"D","预膜","AB","2020版教材P112 分部分项工程量清单，如030801001低压碳钢管，项目特征有：材质，规格，连接形式、焊接方法，压力试验、吹扫与清洗设计要求，脱脂设计要求。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]