[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902221":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902221,583,2,"多选题","根据《建设工程工程量清单计价规范》GB50500-2013的规定，分部分项工程量清单中必须列出的内容有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目特征描述",true,{"key":16,"text":17,"correct":18},"B","工程量计算规则",false,{"key":20,"text":21,"correct":14},"C","计量单位",{"key":23,"text":24,"correct":14},"D","工程量","ACD","2020版教材P114 分部分项工程量清单必须包括五部分，在编制分部分项工程量清单时，最新题库考前黑钻押题，金考典软件考前更新，下载链接 www.jinkaodian.com 应根据《安装工程计量规范》规定的项目编码、项目名称、项目特征、计量单位和工程量计算规则进行编制，各个分部分项工程量清单必须包括五部分：项目编码、项目名称、项目特征、计量单位和工程量，缺一不可。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]