[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902187":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902187,583,2,"多选题","设备气密性试验是用来检验连接部位的密封性能，其遵循的规定有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备经液压试验合格后方可进行气密性试验",true,{"key":16,"text":17,"correct":18},"B","气密性试验的压力应为设计压力的1.15倍",false,{"key":20,"text":21,"correct":14},"C","缓慢升压至试验压力后，保压30min以上",{"key":23,"text":24,"correct":14},"D","连接部位等应用检漏液检查","ACD","2020版教材P109 气密性试验应在耐压试验合格后进行。对进行气压试验的设备，气密性试验可在气压试验压力降到气密性试验压力后一并进行。设备气密性试验方法及要求:（1）设备经液压试验合格后方可进行气密性试验。（2）气密性试验时，压力应缓慢上升，达到试验压力后，保压时间不少于30min,同时对焊缝和连接部位等用检漏液检查，无泄漏为合格。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]