[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902029":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902029,583,2,"多选题","依据《通用安装工程工程量计算规范》（GB50856-2013）的规定，属于安全文明施工项目的有（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","场地排水排污措施",true,{"key":16,"text":17,"correct":14},"B","现场生活卫生设施",{"key":19,"text":20,"correct":21},"C","夜间施工劳动效率降低",false,{"key":23,"text":24,"correct":14},"D","建筑工地起重机械的检验检测","ABD","《安装工程计量规范》附录 N 中提供了安装专业工程可列的措施项目，共 18 条；安全文明施工及其他措施项目，共 7 条。 A．场地排水排污措施 ；B．现场生活卫生设施；D．建筑工地起重机械的检验检测：三项属于安全文明施工（031301001）；C．夜间施工劳动效率降低：属于夜间施工增加（031301002）。此题问的是哪些属于安全文明施工措施项目，所以答案为 ABD。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]