[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902028":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902028,583,2,"多选题","依据《通用安装工程工程量计算规范》（GB50856-2013）的规定，属于安装专业工程措施项目的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","脚手架撘拆",true,{"key":16,"text":17,"correct":18},"B","二次搬运",false,{"key":20,"text":21,"correct":18},"C","已完工程及设备保护",{"key":23,"text":24,"correct":14},"D","管道安拆后的充气保护","AD","《安装工程计量规范》附录 N 中提供了安装专业工程可列的措施项目，共 18 条；安全文明施工及其他措施项目，共 7 条。 脚手架撘拆（031302001）：归类于专业措施项目；管道安拆后的充气保护（031304016）：属于专业措施项目。二次搬运；管道安拆后的充气保护：属于通用措施项目。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]