[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-902027":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},902027,583,2,"多选题","依据《通用安装工程计量规范》（GB50856-2013）的规定，可以列项：“高层施工增加”的情况有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单层建筑物檐口高度超过20m",true,{"key":16,"text":17,"correct":18},"B","多层建筑物超过8 层",false,{"key":20,"text":21,"correct":18},"C","单层建筑物檐口高度超过15m",{"key":23,"text":24,"correct":14},"D","多层建筑物超过6 层","AD","高层施工增加：高层施工引起的人工工效降低以及由于人工工效降低引起的机械降效。通讯联络设备的使用及摊销。 1）单层建筑物檐口高度超过20m，多层建筑物超过6 层时，应分别列项。 2）高层施工增加指突出主体建筑物顶的电梯机房、楼梯出口间、水箱间、瞭望塔、排烟机房等不计入檐口高度。计算层数时，地下室不计入层数。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]