[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901948":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901948,583,2,"多选题","(2013年)衬胶管道的管段、管件经机械加工、焊接、热处理后，在衬里前应进行的工序是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编号",true,{"key":16,"text":17,"correct":14},"B","预装",{"key":19,"text":20,"correct":21},"C","充氮",false,{"key":23,"text":24,"correct":14},"D","试压及检验","ABD","(5）管段及管件的机械加工， 焊接、热处理等应在衬里前进行完毕， 并经预装、编号、试压及检验合格。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]