[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901895":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901895,583,2,"多选题","(2016年)依据《通用安装工程工程量计算规范》GB50856-2013的规定，消防工程工程量计量时，下列装置按“组”计算的有()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","消防水炮",false,{"key":16,"text":17,"correct":18},"B","报警装置",true,{"key":20,"text":21,"correct":18},"C","末端试水装置",{"key":23,"text":24,"correct":18},"D","温感式水幕装置","BCD","该题主要考察的是：消防工程工程量计量，消防水炮按“台”计量；报警装置、温感式水幕装置按型号、规格以“组”计算：末端试水装置按规格、组装形式以“组”计算。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]