[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901885":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901885,583,2,"多选题","(2017年)依据《通用安装工程工程量计算规范》(GB50856-2013)的规定，中压锅炉及其他辅助设备安装工程量计量时，以“只”为计量单位的项目有()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","省煤器",false,{"key":16,"text":17,"correct":18},"B","煤粉分离器",true,{"key":20,"text":21,"correct":18},"C","暖风器",{"key":23,"text":24,"correct":14},"D","旋风分离器","BC","(7)中压锅炉其他辅助设备安装。 2）暖风器应根据项目特征（名称、型号、出力、结构形式、质量）， 以“ 只” 为计量单位， 按设计图示质量计算。 4）煤粉分离器应根据项目特征（结构类型、直径、质量）， 以“ 只” 为计量单位， 按设计图示质量计算。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]