[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901883":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901883,583,2,"多选题","(2013年)根据《通用安装工程工程量计算规范》热力设备安装工程按设计图示设备质量以“t”计算的有()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","烟道、热风道",true,{"key":16,"text":17,"correct":14},"B","渣仓",{"key":19,"text":20,"correct":14},"C","脱硫吸收塔",{"key":22,"text":23,"correct":24},"D","除尘器",false,"ABC","该题主要考察的是热力设备安装计量，A项烟道、热风道、冷风道、制粉管道、送粉管道、原煤管道应根据项目特征（管道形状、管道断面尺寸、管壁厚度），以“ t” 为计量单位，按设计图示质量计算。B项渣仓应根据项目特征［容积（m3 ）、钢板厚度］， 以“ t” 为计量单位， 按设计图示设备质量计算。C项石粉仓、吸收塔应根据项目特征［型号、出力（t\u002Fh）、容积或直径］， 以“ t” 为计量单位，按设计图示质量计算。D项废热锅炉、废热锅炉竖管、除滴器、旋涡除尘器、除灰水封、隔离水封， 应按设备的不同名称及不同直径和高度， 分别以“台” 为单位计算。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]