[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901878":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901878,583,2,"多选题","(2018年)依据《通用安装工程工程量计算规范》（GB 50856－2013），机械设备安装工程量中以“台”为计量单位的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直流电梯安装",false,{"key":16,"text":17,"correct":18},"B","冷水机组",true,{"key":20,"text":21,"correct":18},"C","多级离心泵安装",{"key":23,"text":24,"correct":14},"D","风力发电机","BC","直流电梯以“部”为计量单位；风力发电机以“组”为计量单位；冷水机组、多级离心泵以“台”为计量单位。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]