[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901864":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901864,583,2,"多选题","(2014年)依据《建设工程工程量清单计价规范》(GB50500-2013)的规定，安装工程量清单中的其他项目清单除包括暂估价外，一般还有()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","暂列金额",true,{"key":16,"text":17,"correct":14},"B","计日工",{"key":19,"text":20,"correct":21},"C","分包服务费",false,{"key":23,"text":24,"correct":14},"D","总承包服务费","ABD","该题主要考察的是其他项目清单包括内容，其他项目清单应根据拟建工程的具体情况确定。一般包括暂列金额、暂估价、计日工和总承包服务费等。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]