[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901863":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901863,583,2,"多选题","(2014年)依据《通用安装工程工程量计算规范》(GB50856-2013)的规定，项目安装高度若超过基本高度时，应在项目特征中描述。附录中基本安装高度为6m的项目名称为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","附录G通风空调工程",true,{"key":16,"text":17,"correct":18},"B","附录J消防工程",false,{"key":20,"text":21,"correct":18},"C","附录K给排水、采暖、燃气工程",{"key":23,"text":24,"correct":14},"D","附录M刷油、防腐蚀、绝热工程","AD","该题主要考察的是项目安装高度，依据《通用安装工程工程量计算规范》(GB508562013)的规定，项目安装高度若超过基本高度时，应在项目特征中描述。《通用安装工程工程量计算规范》安装工程各附录基本安装高度为：附录A机械设备安装工程10m；附录D电气设备安装工程5m；附录E建筑智能化工程5m；附录G通风空调工程6m；附录J消防工程5m；附录K给排水、采暖、燃气工程3.6m；附录M刷油、防腐蚀、绝热工程6m。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]