[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901862":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901862,583,2,"多选题","(2017年)依据《通用安装工程工程量计算规范》(GB50856-2013)，其他项目清单中的暂列金额包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程合同签订时尚未确定或者不可预见的所需材料、工程设备、服务的采购等费用",true,{"key":16,"text":17,"correct":18},"B","施工过程中出现质量问题或事故的处理费用",false,{"key":20,"text":21,"correct":14},"C","施工中可能发生工程变更所需费用",{"key":23,"text":24,"correct":14},"D","合同约定调整因素出现时的合同价款调整及发生的索赔、现场签证确认等的费用","ACD","(1）暂列金额。招标人在工程量清单中暂定并包括在合同价款中的一笔款项。用于工程合同签订时尚未确定或者不可预见的所需材料、工程设备、服务的采购， 施工中可能发生的工程变更、合同约定调整因素出现时的合同价款调整以及发生的索赔、现场签证确认等的费用。暂列金额应根据工程特点， 按有关计价规定估算。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]