[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901856":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901856,583,2,"多选题","(2014年)依据《通用安装工程工程量计算规范》(GB50856-2013)的规定，属于安全文明施工及其他措施项目的有()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在有害身体健康环境中施工增加",false,{"key":16,"text":17,"correct":18},"B","环境保护",true,{"key":20,"text":21,"correct":18},"C","非夜间施工增加",{"key":23,"text":24,"correct":18},"D","高层施工增加","BCD","该题主要考察的是安全文明施工及其他措施项目内容，通用措施项目一览表中安全文明施工及其他措施项目有：环境保护；文明施工；安全施工；临时设施；夜间施工增加；非夜间施工增加；二次搬运；冬雨季施工增加；已完工程及设备保护；高层施工增加及其他。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]