[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901854":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901854,583,2,"多选题","(2013年)根据《通用安装工程工程量计算规范》，属于安装专业措施项目的有()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","脚手架搭拆",true,{"key":16,"text":17,"correct":18},"B","冬雨季施工增加",false,{"key":20,"text":21,"correct":14},"C","特殊地区施工增加",{"key":23,"text":24,"correct":18},"D","已完工程及设备保护","AC","该题主要考察的是专业措施项目内容，专业措施项目有：吊装加固；金属抱杆安装、拆除、移位；平台铺设、拆除；顶升、提升装置；大型设备专用机具；焊接工艺评定；胎（模）具制作、安装、拆除；防护棚制作、安装、拆除；特殊地区施工增加；安装与生产同时进行施工增加；在有害身体健康环境中施工增加；工程系统检测、检验；设备、管道施工的安全、防冻和焊接保护；焦炉烘炉、热态工程；管道安拆后的充气保护；隧道内施工的通风、供水、供气、供电、照明及通信设施；脚手架搭拆；其他措施。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]