[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901853":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901853,583,2,"多选题","(2018年)编制一份分部分项工程量清单应包括五个要件，它们是项目编码及（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目名称",true,{"key":16,"text":17,"correct":14},"B","项目特征",{"key":19,"text":20,"correct":14},"C","计量单位",{"key":22,"text":23,"correct":24},"D","工程量计算规则",false,"ABC","在编制分部分项工程量清单时，必须根据相关工程现行国家计量规范规定的项目编码、项目名称、项目特征、计量单位和工程量计算规则进行编制，即一个分部分项工程量清单应包括五个要件：项目编码、项目名称、项目特征、计量单位和工程量这五个要件在分部分项工程项目清单的组成中缺一不可。",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]