[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901844":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901844,583,2,"多选题","(2011年)管道进行水压试验时，试压前的准备工作包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","安装临时注水和排水管线",true,{"key":16,"text":17,"correct":14},"B","管道系统的最高点安装排气阀",{"key":19,"text":20,"correct":14},"C","管道系统的末端安装排气阀",{"key":22,"text":23,"correct":24},"D","管道系统的最低点安装压力表",false,"ABC","该题主要考察的是：管道液压试验的方法和要求中试压前的准备工作相关内容，“试压前的准备工作。安装试验用的临时注水和排水管线；在试验管道系统的最高点和管道末端安装排气阀；在管道的最低处安装排水阅；压力表应安装在最高点，试验压力以此表为准。”",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]