[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901816":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},901816,583,2,"多选题","(2016年)依据《通用安装工程工程量计算规范》GB50856-2013的规定，静置设备安装中的整体容器安装项目，根据项目特征描述范围，其他工作内容包括容器安装，吊耳制作，安装外，还包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备填充",false,{"key":16,"text":17,"correct":18},"B","压力试验",true,{"key":20,"text":21,"correct":18},"C","清洗、脱脂、钝化",{"key":23,"text":24,"correct":18},"D","灌浆","BCD","《通用安装工程工程量计算规范》GB50856-2013：",{"id":6,"name":28,"category":29,"favorite":30},"建设工程技术与计量（安装)","建筑工程",0]