[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},901722,583,1,"单选题","（2017年考题）蒸汽夹套管系统安装完毕后，应用低压蒸汽吹扫，正确的吹扫顺序应为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主管→支管→夹套管环隙",true,{"key":16,"text":17,"correct":18},"B","支管→主管→夹套管环隙",false,{"key":20,"text":21,"correct":18},"C","主管→夹套管环隙→支管",{"key":23,"text":24,"correct":18},"D","支管→夹套管环隙→主管","夹套管安装构成系统后，应进行内、外管的吹扫工作，凡不能参与吹扫的管道、设备、阀门、仪表等，应拆除或用盲板隔离。热水夹套系统的吹扫要求同内管。而蒸汽夹套系统用低压蒸汽吹扫，吹扫顺序为先主管、后支管，最后进入夹套管的环隙。操作时需充分暖管，缓慢开启控制阀门升温，恒温60min后连续吹扫10～20min，重复3～4次。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]