[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-901610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},901610,583,1,"单选题","（2016年考题）下列有关工业锅炉本体安装的说法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","锅筒内部装置的安装应在水压试验合格后进行",true,{"key":16,"text":17,"correct":18},"B","水冷壁和对流管束一端为焊接、另一端为胀接时，应先胀后焊",false,{"key":20,"text":21,"correct":18},"C","铸铁省煤器整体安装完后进行水压试验",{"key":23,"text":24,"correct":18},"D","对流过热器大多安装在锅炉的顶部","选项B，水冷壁和对流管束管子—端为焊接、另一端为胀接时，应先焊后胀，并且管子上全部附件应在水压试验之前焊接完毕。选项C，铸铁省煤器安装前，应逐根（或组）进行水压试验，可避免锅炉水压试验时发生泄漏而拆装换管的麻烦。选项D，对流过热器大都垂直悬挂于锅炉尾部，辐射过热器多半装于锅炉的炉顶部或包覆于炉墙内壁上。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（安装)","建筑工程",0]